363) A Welding Operation Is Time-studied During Which An Operator Was Pace-rated As 120%. The Operator Took, On An Average, 8 Minutes For Producing The Weld-joint. If A Total Of 10% Allowances Are Allowed For This Operation, The Expected Standard Production Rate Of The Weld-joint (in Units Per 8 Hour Day) Is
45
50
55
60