374) A Maintenance Service Facility Has Poisson Arrival Rates, Negative Exponential Service Time And Operates On A ‘first Come First Served’ Queue Discipline. Break Downs Occur On An Average Of 3 Per Day With A Range Of Zero To Eight. The Maintenance Crew Can Service An Average Of 6 Machines Per Day With A Range Of Zero To Seven. The Mean Waiting Time For An Item To Be Serviced Would Be
16 Day
13 Day
1 Day
3 Days
Hint
No Hint Found
Previous | Medium (Difficulty Level)| Next
Previous | Mechanical ( Category) | Next
Previous | Date Wise (As Submitted)| Next
This is Medium Level Question in English Language Posted By Sunil Saharan in Engineering --> Mechanical Category (Viewed : 76 Times)
Sunil Saharan Real Photo
Sunil Saharan Avatar

Sunil SaharanAn Engineer

I'm Sunil Saharan, An Electrical Engineer by chance and a Web developer by choice. I love HTML, CSS, JS, Bootstrap and PHP off course. This site is my effort to share my little knowlege with the world.

उदय होते समय सूर्य लाल होता है और अस्त होते समय भी। इसी प्रकार संपत्ति और विपत्ति के समय महान पुरुषों में एकरूपता होती है।

-- कालिदास
Site Statistics
Stats at a Glance

Articles: 46
Viewed: 237351 Times
Photos : 53
Viewed: 515780 Times
Questions : 2344
Viewed: 137698 Times
Page Load No. 1036528

Articles
Photos
Take Quiz
1 Liners For Exam
Show Questions(1 by 1)
© 2011-2018 @   www.SunilSaharan.in